Project Schedule

The schedule for Preliminary Engineering and Environmental Assessment of the KY 55 Heartland Parkway spans a five-year period.  Many interdependent steps are involved in the process of integrating design with public involvement and environmental documentation.  The major milestones for this project are as follows:

Public Meeting No. 1 October 2007
Focus Group Meeting No. 1 December 2007
Public Meeting No. 2:  Stage 1 Alternatives March 2009
Focus Group Meeting No. 2 May 2009
Public Meeting No. 3:  Stage 2 Alternatives September 2009
Focus Group Meeting No. 3 January 2011
Approval of Environmental Base Studies February 2011
Approval of Environmental Assessment by FHWA May 2011
Public Hearings September 2011
Focus Group Meeting No. 4 November 2011
FHWA Approval of Preferred Alternative August 2012